Construction Update – Hyegrove

October 2023

Estimated Construction Completion: Early 2025
Estimated Settlement: Early 2025

We wish to advise that building work continues to progress well.
Please see the construction update for the past quarter below:

Milestones:

  • Bulk & detailed earthworks complete
  • Shoring complete
  • Cranes 01 & 02 erected
  • Concrete Tower Boom erected
  • All pad footings & lift pits poured
  • Inground services complete
  • OSD tank slab and walls poured
  • OSD pump out pit and sewer tank installed
  • 100% of all slabs on the ground basement 03 have been poured
  • 50% of basement 02 concrete slabs have been poured
  • 80% of basement 02 formwork have been erected
  • 20% of level 1 podium have been prepped ready to be poured
  • 50% of level 1 podium formwork have been erected

Works planned on site for the first quarter of 2023:

  • 100% Basement 02 concrete slabs to be poured
  • 100% Basement ramps to be poured
  • 100% Basement 01 concrete slabs to be poured
  • 100% Podium levels to be poured
  • Building C – structure to be completed
  • Building B – structure to be 80%
  • Basement High-Level Services rough-ins commenced
  • Basement Soffits & Columns painting commenced
  • Building D (RACF) – Commence Structure
  • Building A – Commence Structure

Programme

The key programme items are as follows:

  1. Site set up works – Completed
  2. Demolition – Completed
  3. Shoring Works – Completed
  4. Bulk Earthworks – Completed
  5. Detailed Excavation – Completed
  6. Basement works – In Progress
  7. Structure works – In Progress
  8. Services rough in – In Progress
  9. Window glazing – Not Started
  10. Facade cladding – Not Started
  11. Internal fit out works – Not Started
  12. Club Works – Not Started
  13. Finishing works – Not Started
  14. Landscaping – Not started
  15. Title registration – Not started
  16. Ready to settle –