Estimated Construction Completion: Early 2025
Estimated Settlement: Early 2025
Click here to view Hyegrove Willoughby construction timeline and 360-degree views.
We wish to advise that building work continues to progress well.
Please see the construction update for the past quarter below:
Milestones:
- Bulk & detailed earthworks complete
- Shoring complete
- Cranes 01 & 02 erected
- Concrete Tower Boom erected
- All pad footings & lift pits poured
- Inground services complete
- OSD tank slab and walls poured
- OSD pump out pit and sewer tank installed
- 100% of all slabs on the ground basement 03 have been poured
- 50% of basement 02 concrete slabs have been poured
- 80% of basement 02 formwork have been erected
- 20% of level 1 podium have been prepped ready to be poured
- 50% of level 1 podium formwork have been erected
Works planned on site for the first quarter of 2023:
- 100% Basement 02 concrete slabs to be poured
- 100% Basement ramps to be poured
- 100% Basement 01 concrete slabs to be poured
- 100% Podium levels to be poured
- Building C – structure to be completed
- Building B – structure to be 80%
- Basement High-Level Services rough-ins commenced
- Basement Soffits & Columns painting commenced
- Building D (RACF) – Commence Structure
- Building A – Commence Structure
Programme
The key programme items are as follows:
- Site set up works – Completed
- Demolition – Completed
- Shoring Works – Completed
- Bulk Earthworks – Completed
- Detailed Excavation – Completed
- Basement works – In Progress
- Structure works – In Progress
- Services rough in – In Progress
- Window glazing – Not Started
- Facade cladding – Not Started
- Internal fit out works – Not Started
- Club Works – Not Started
- Finishing works – Not Started
- Landscaping – Not started
- Title registration – Not started
- Ready to settle –