Estimated Construction Completion: July 2023
Estimated Settlement: August 2023
Click here to view Tara Lane Cove construction timeline and 360-degree views.
Over the past three months the Hyecorp team have been very busy progressing construction on Tara in readiness for
completion in July.
Please see the construction update below:
Milestones:
- Completion of Façade
- Completion of all Landscaping works to property
boundaries, units and rooftop garden - Internal fit out continuing and moving into final quality
checks and commissioning - Basements Linemarked and Storage Cages installed
- Strata Plan Registered
Programme
The key programme items are as follows:
- Site set up works – Completed
- Bulk excavation – Completed
- Basement works – Completed
- Structure works – Completed
- Services rough in – Completed
- Window glazing – Completed
- Facade cladding – Completed
- Internal fit out works – Completed
- Finishing works – Completed
- Landscaping – Completed
- Title registration – Completed
- Ready to settle – August 2023 (subject to issue date of OC)