Construction Update – Tara

July 2023

Over the past three months the Hyecorp team have been very busy progressing construction on Tara in readiness for
completion in July.

Please see the construction update below:

Milestones:

  • Completion of Façade
  • Completion of all Landscaping works to property
    boundaries, units and rooftop garden
  • Internal fit out continuing and moving into final quality
    checks and commissioning
  • Basements Linemarked and Storage Cages installed
  • Strata Plan Registered

Programme

The key programme items are as follows:

  1. Site set up works – Completed
  2. Bulk excavation – Completed
  3. Basement works – Completed
  4. Structure works – Completed
  5. Services rough in – Completed
  6. Window glazing – Completed
  7. Facade cladding – Completed
  8. Internal fit out works – Completed
  9. Finishing works – Completed
  10. Landscaping – Completed
  11. Title registration – Completed
  12. Ready to settle – August 2023 (subject to issue date of OC)