Estimated Construction Completion: Q2 2023
Estimated Settlement: Q3 2023
Click here to view Tara Lane Cove construction timeline and 360-degree views.
We wish to advise that building work continues to progress well.
Please see the construction update for the past quarter below:
Milestones:
- Lift 2 Commissioned
- Perimeter Scaffold Removed to the East, South & West Elevations
- Crane Removed from Site
- Commencement of Landscaping Works
- Kitchen joinery and appiances installed. Floorboards layed
Works planned on site for the next quarter of 2023:
- Lift 1 Commissioning
- Completion of Façade & External Works
- Completion of Rooftop Garden Fitout
- Scaffold dismantle and removal for Northern face
- Completion of Units & Lobbies for Settlement
Programme
The key programme items are as follows:
- Site set up works – Completed
- Bulk excavation – Completed
- Basement works – Completed
- Structure works – Completed
- Services rough in – Completed
- Window glazing – Completed
- Facade cladding – Near Completion
- Internal fit out works – Near Completion
- Finishing works – In Progress
- Landscaping – Not started
- Title registration – In Progress
- Ready to settle – July 2023