Construction Update – Tara

January 2023

Estimated Construction Completion: 2nd quarter 2023
Estimated Settlement: July 2023

We wish to advise that building work continues to progress well.
Please see the construction update for the past quarter below:

Milestones:

  • Structure Complete
  • Level 4 Fit-out Commenced
  • Lift 2 Installed
  • External Works Commenced

Works planned on site for the next quarter of 2023:

  • Scaffold removed
  • Permanent Power
  • Water and Gas Connection
  • Complete Fit-out
  • Rooftop Garden Fit-out
  • Full building commissioning

Programme

The key programme items are as follows:

  1. Site set up works – Completed
  2. Bulk excavation – Completed
  3. Basement works – Completed
  4. Structure works – Completed
  5. Services rough in – In Progress
  6. Window glazing – In Progress
  7. Facade cladding – In Progress
  8. Internal fit out works – In Progress
  9. Finishing works – In Progress
  10. Landscaping – Not started
  11. Title registration – In Progress
  12. Ready to settle –