Estimated Construction Completion: 2nd quarter 2023
Estimated Settlement: July 2023
Click here to view Tara Lane Cove construction timeline and 360-degree views.
We wish to advise that building work continues to progress well.
Please see the construction update for the past quarter below:
Milestones:
- Structure Complete
- Level 4 Fit-out Commenced
- Lift 2 Installed
- External Works Commenced
Works planned on site for the next quarter of 2023:
- Scaffold removed
- Permanent Power
- Water and Gas Connection
- Complete Fit-out
- Rooftop Garden Fit-out
- Full building commissioning
Programme
The key programme items are as follows:
- Site set up works – Completed
- Bulk excavation – Completed
- Basement works – Completed
- Structure works – Completed
- Services rough in – In Progress
- Window glazing – In Progress
- Facade cladding – In Progress
- Internal fit out works – In Progress
- Finishing works – In Progress
- Landscaping – Not started
- Title registration – In Progress
- Ready to settle –