Construction Update – Kira

February 2022

Milestones:

  • All scaffolding has now been removed.
  • We will be commencing all the external footpath and kerb and gutter works on Mowbray Road and Mindarie Street.
  • Landscaping has now commenced along the ground floor and will be completed in 2 months’ time.
  • Commencement of the rooftop garden and common area fitout.
  • Lodgement of the strata plan expected this month.
  • Section 73 certificate expected to be issued this month.
  • Internal fit out continuing and moving into defect checks and commissioning.
  • Tower crane was removed.
Works planned on site for the next quarter of 2022:
  • Complete fit out works.
  • Complete all ground floor and rooftop landscaping.
  • Completion of all civil works footpath and kerb and gutters.
  • Strata plan registered.
  • Prepare for occupational certificate.

Click here to view Kira Lane Cove construction timeline and 360-degree views.