Milestones:
- All scaffolding has now been removed.
- We will be commencing all the external footpath and kerb and gutter works on Mowbray Road and Mindarie Street.
- Landscaping has now commenced along the ground floor and will be completed in 2 months’ time.
- Commencement of the rooftop garden and common area fitout.
- Lodgement of the strata plan expected this month.
- Section 73 certificate expected to be issued this month.
- Internal fit out continuing and moving into defect checks and commissioning.
- Tower crane was removed.
Works planned on site for the next quarter of 2022:
- Complete fit out works.
- Complete all ground floor and rooftop landscaping.
- Completion of all civil works footpath and kerb and gutters.
- Strata plan registered.
- Prepare for occupational certificate.
Click here to view Kira Lane Cove construction timeline and 360-degree views.