Construction Update – Kira

September 2021

Milestones:

  • Site is progressing well with all plasterboard walls completed and now well into fit out of the apartments.
  • Kitchen and wardrobe joinery commenced and midway along with wet area tiling.
  • Façade rendering and metalworks commenced and well underway.
  • The watermain extension is heading towards completion and expected to be completed by end of this month.
  • Permanent power to the building is now installed on site.
Works planned on site for the next quarter of 2021:
  • Complete façade elements and remove all scaffolding.
  • Complete all footpath and civil works.
  • Complete basement fit out line marking and storage cages.
  • Complete fit out of residential apartments.

Click here to view Kira Lane Cove construction timeline and 360-degree views.