Construction Update – Juliet

February 2025

Estimated Construction Completion: 2026
Estimated Settlement: Early 2026

Click here to view a timeline of the build go to our 360 photo captured in July 2024

We wish to advise that building work continues to progress well.
Please see the construction update below:

Milestones:

  • Commence Works On-site
  • Site Establishment – Complete
  • Demolition Works – Complete
  • Tree Lopping & Pruning – Complete
  • Site Levelling – Commenced

Works planned on site for the next quarter
(January – March 2025):

  • Receipt of Construction Certificate No.1 (Demolition/Shoring & Excavation)
  • Piling Complete
  • Capping Beam Complete
  • Commencement of Bulk Excavation

Programme

The key programme items are as follows:

  1. Site set up works Complete
  2. Demolition Complete
  3. Bulk excavation Not started
  4. Basement works Not started
  5. Structure works Not started
  6. Services rough in Not started
  7. Window glazing Not started
  8. Facade cladding Not started
  9. Internal fit out works Not started
  10. Finishing works Not started
  11. Landscaping Not started
  12. Title registration Not started
  13. Ready to settle –

Next Update: April 2025