Estimated Construction Completion: 2026
Estimated Settlement: Early 2026
Click here to view a timeline of the build go to our 360 photo captured in July 2024
We wish to advise that building work continues to progress well.
Please see the construction update below:
Milestones:
- Commence Works On-site
- Site Establishment – Complete
- Demolition Works – Complete
- Tree Lopping & Pruning – Complete
- Site Levelling – Commenced
Works planned on site for the next quarter
(January – March 2025):
- Receipt of Construction Certificate No.1 (Demolition/Shoring & Excavation)
- Piling Complete
- Capping Beam Complete
- Commencement of Bulk Excavation

Programme
The key programme items are as follows:
- Site set up works Complete
- Demolition Complete
- Bulk excavation Not started
- Basement works Not started
- Structure works Not started
- Services rough in Not started
- Window glazing Not started
- Facade cladding Not started
- Internal fit out works Not started
- Finishing works Not started
- Landscaping Not started
- Title registration Not started
- Ready to settle –
Next Update: April 2025