Estimated Construction Completion: Early 2025
Estimated Settlement: Early 2025
Click here to view a timeline of the build go to our 360 photo captured in January 2025
We wish to advise that building work continues to progress well.
Please see the construction update below:
Milestones:
September – December 2024
- Basement 03 – Cleaned with Storage Cage installation complete.
- Basement 02 – High-Level Services rough-ins complete.
- Basement 01 – Services Rough-in Complete.
- Building C – final fit off and lock-up to Units.
- Building B – final fit off and lock-up to Units up to Level 2.
- Building D – above ceiling services rough-ins, internal walls sheeted, and bathroom fit off commenced.
- Building A – internal wall sheeting, windows, waterproofing, tiling and joinery installation complete up to Level 5.
- Building E – internal wall sheeting, windows up to Level 4. Waterproofing and Tiling to Level 2.
- Building F (Club Willougby) – Structure Complete, above ceiling services rough-ins, internal and external wall framing,
waterproofing, and window prep to up to Level 2. - Façade & Scaffold Stripping to Buildings B & Commenced on A.
- Building A Common Areas Level 1 & Level 2 – Internal framing and sheeting commenced to walls and ceiling.

Works planned on site for the next quarter of 2025:
January – March 2025
- Basement 01 – Blockwork wall construction complete.
- Basement 02 – High-Level Services rough-ins complete.
- Basement 01 – Soffits & Columns painting complete.
- Basement 01 – Soffit Insulation Complete.
- Building C – final fit off and lock-up to Units.
- Building B – final fit off and lock-up to Units up to Level 3.
- Building D – above ceiling services rough-ins, internal and external wall framing, waterproofing, and window prep complete.
- Building A – internal wall sheeting, windows, waterproofing, tiling and joinery installation complete up to Level 4.
- Building E – above ceiling services rough-ins, internal and external wall framing and window prep complete.
- Building F (Club Willougby) – Structure Complete, above ceiling services rough-ins, internal and external wall framing, waterproofing, and window prep to commence up to Level 2.
- Façade & Scaffold Stripping to Buildings B & D.


Programme
The key programme items are as follows:
- Site set up works Completed
- Demolition Completed
- Shoring Works Completed
- Bulk Earthworks Completed
- Detailed Excavation Completed
- Basement works In Progress
- Structure works In Completed
- Services rough in In Progress
- Window glazing In Progress
- Facade cladding In Progress
- Internal fit-out works In Progress
- Club Works Not Started
- Finishing works Not Started
- Landscaping Not Started
- Title registration Not Started
- Ready to settle –
Next Update: April 2025