Construction Update – Hyegrove

February 2025

Estimated Construction Completion: Early 2025
Estimated Settlement: Early 2025

Click here to view a timeline of the build go to our 360 photo captured in January 2025

We wish to advise that building work continues to progress well.
Please see the construction update below:

Milestones:

September – December 2024

  • Basement 03 – Cleaned with Storage Cage installation complete.
  • Basement 02 – High-Level Services rough-ins complete.
  • Basement 01 – Services Rough-in Complete.
  •  Building C – final fit off and lock-up to Units.
  •  Building B – final fit off and lock-up to Units up to Level 2.
  • Building D – above ceiling services rough-ins, internal walls sheeted, and bathroom fit off commenced.
  • Building A – internal wall sheeting, windows, waterproofing, tiling and joinery installation complete up to Level 5.
  • Building E – internal wall sheeting, windows up to Level 4. Waterproofing and Tiling to Level 2.
  • Building F (Club Willougby) – Structure Complete, above ceiling services rough-ins, internal and external wall framing,
    waterproofing, and window prep to up to Level 2.
  • Façade & Scaffold Stripping to Buildings B & Commenced on A.
  • Building A Common Areas Level 1 & Level 2 – Internal framing and sheeting commenced to walls and ceiling.

Works planned on site for the next quarter of 2025:

January – March 2025

  • Basement 01 – Blockwork wall construction complete.
  • Basement 02 – High-Level Services rough-ins complete.
  • Basement 01 – Soffits & Columns painting complete.
  • Basement 01 – Soffit Insulation Complete.
  • Building C – final fit off and lock-up to Units.
  • Building B – final fit off and lock-up to Units up to Level 3.
  • Building D – above ceiling services rough-ins, internal and external wall framing, waterproofing, and window prep complete.
  • Building A – internal wall sheeting, windows, waterproofing, tiling and joinery installation complete up to Level 4.
  • Building E – above ceiling services rough-ins, internal and external wall framing and window prep complete.
  • Building F (Club Willougby) – Structure Complete, above ceiling services rough-ins, internal and external wall framing, waterproofing, and window prep to commence up to Level 2.
  • Façade & Scaffold Stripping to Buildings B & D.

Programme

The key programme items are as follows:

  1. Site set up works Completed
  2. Demolition Completed
  3. Shoring Works Completed
  4. Bulk Earthworks Completed
  5. Detailed Excavation Completed
  6. Basement works In Progress
  7. Structure works In Completed
  8. Services rough in In Progress
  9. Window glazing In Progress
  10. Facade cladding In Progress
  11. Internal fit-out works In Progress
  12. Club Works Not Started
  13. Finishing works Not Started
  14. Landscaping Not Started
  15. Title registration Not Started
  16. Ready to settle –

Next Update: April 2025