Construction Update – Hyegrove

October 2024

Estimated Construction Completion: Early 2025
Estimated Settlement: Early 2025

Click here to view a timeline of the build go to our 360 photo captured in December 2023

We wish to advise that building work continues to progress well.
Please see the construction update below:

Milestones:

  • Basement 02 & 03 – Blockwork wall construction complete
  • Basement 03 – High-Level Services rough-ins complete
  • Basement 02 & 03 – Soffits & Columns painting complete
  • Basement 02 & 03 – Soffit Insulation Complete
  • Building C – internal wall sheeting, windows, waterproofing complete. Tiling and joinery installation underway.
  • Building B – internal wall sheeting and windows complete. Waterproofing, tiling and joinery installation underway.
  • Building D – above ceiling services rough-ins, internal and external wall framing and window prep complete.
  • Building A – Structure complete, above ceiling services roughins, internal and external wall framing complete. Wall sheeting up to Level 2.
  • Building E – Structure complete and stripping of formwork materials underway. above ceiling services rough-ins, internal and external wall framing, waterproofing, and window prep to commence up to Level 2
  • Building F (Club Willougby) – Structure up to Roof Level.
  • Façade & Scaffold Stripping to Buildings C

Works planned on site for the fourth quarter of 2024:

  • Basement 01 – Blockwork wall construction complete
  • Basement 02 – High-Level Services rough-ins complete
  • Basement 01 – Soffits & Columns painting complete
  • Basement 01 – Soffit Insulation Complete
  • Building C – final fit off and lock-up to Units.
  • Building B – final fit off and lock-up to Units up to Level 3.
  • Building D – above ceiling services rough-ins, internal and external wall framing, waterproofing, and window prep complete.
  • Building A – internal wall sheeting, windows, waterproofing, tiling
    and joinery installation complete up to Level 4.
  • Building E – above ceiling services rough-ins, internal and external wall framing and window prep complete.
  • Building F (Club Willougby) – Structure Complete, above ceiling services rough-ins, internal and external wall framing, waterproofing, and window  prep to commence up to Level 2
  • Façade & Scaffold Stripping to Buildings B & D

Programme

The key programme items are as follows:

  1. Site set up works Completed
  2. Demolition Completed
  3. Shoring Works Completed
  4. Bulk Earthworks Completed
  5. Detailed Excavation Completed
  6. Basement works Completed
  7. Structure works In Progress
  8. Services rough in In Progress
  9. Window glazing In Progress
  10. Facade cladding In Progress
  11. Internal fit-out works In Progress
  12. Club Works Not Started
  13. Finishing works Not Started
  14. Landscaping Not Started
  15. Title registration Not Started
  16. Ready to settle –

Next Update: January 2025