Estimated Construction Completion: Early 2025
Estimated Settlement: Early 2025
Milestones:
- Bulk & detailed
- earthworks complete
- Shoring complete
- Cranes 01 & 02 erected
- Concrete Tower Boom erected
- All pad footings & lift pits poured
- Inground services complete
- OSD tank slab and walls poured
- OSD pump out pit and sewer tank installed
- 100% of all slabs on the ground basement 03 have been poured
- 100% of basement 02 concrete slabs have been poured
- 60% of level 1 podium have been poured
- 85% of level 1 podium formwork have been erected
- Building C – levels 2 & 3 formed and poured
- Building B – level 2 formwork commenced
- Scaffold to building B up to level 03 erected, Scaffold to
- building C up to level 4 erected.
- Ramps between basement 02 to Level 1 are completed
Works planned on site for the first quarter of 2024:
- 100% Basement 01 concrete slabs to be poured
- 100% Podium levels to be poured
- Building C – structure to be completed
- Building B – structure to be completed
- Building A – Levels 2, 3 & 4 to be poured. Level 5 formed
- Building D – Levels 2 & 3 to be poured & Level 4 formed
- Building E – Levels 2 & 3 to formed
- Building F – Level 1 to be poured and level 2 to be formed
- Basement 02 & 03 – Blockwork wall construction commenced
- Basement 03 – High-Level Services rough-ins complete
- Basement 02 – High-Level Services rough-ins commenced
- Lift delivery
- Basement Soffits & Columns painting completed
- Basement Soffit Insulation to have commenced
- Building C – above ceiling services rough-ins, internal and external wall framing, waterproofing, and window prep to commence
- Building B – above ceiling services rough-ins, internal and external wall framing, waterproofing, and window prep to commence
- Building A – Levels 2 & 3 above ceiling services rough-ins, internal and external wall framing, waterproofing, and window prep to commence
Programme
The key programme items are as follows:
- Site set up works Completed
- Demolition Completed
- Shoring Works Completed
- Bulk Earthworks Completed
- Detailed Excavation Completed
- Basement works In Progress
- Structure works In Progress
- Services rough in In Progress
- Window glazing In Progress
- Facade cladding In Progress
- Internal fit-out works In Progress
- Club Works Not Started
- Finishing works Not Started
- Landscaping Not Started
- Title registration Not Started
- Ready to settle –