Construction Update – Hyegrove

July 2023

Estimated Construction Completion: Early 2025
Estimated Settlement: Early 2025

We wish to advise that building work continues to progress well.
Please see the construction update for the past quarter below:

Milestones:

  • Piling Complete
  • Capping Beams Complete
    • Shotcreting and Temp Anchors – 100% Complete
  • Approx. 100,000m³ of soil removed off site
  • Detail Excavation is 50% completed
  • Crane 01 has been erected
  • Pad footings on Level 2 basement on the East Side of the site have been poured
  • Inground services have commenced
  • Main Sewer is installed

Works planned on site for the first quarter of 2023:

  • Erection of Crane 02
  • Continuation of pouring basement slabs on ground
  • Installation of Footings and Pad Footings
  • Completion of Bulk Excavation
  • Erection of first suspended slabs

Programme

The key programme items are as follows:

  1. Site set up works – Completed
  2. Demolition – Completed
  3. Shoring Works – In Progress
  4. Bulk Earthworks – In Progress
  5. Detailed Excavation – In Progress
  6. Basement works – In Progress
  7. Structure works – Not Started
  8. Services rough in – Not Started
  9. Window glazing – Not Started
  10. Facade cladding – Not Started
  11. Internal fit out works – Not Started
  12. Club Works – Not Started
  13. Finishing works – Not Started
  14. Landscaping – Not started
  15. Title registration – Not started
  16. Ready to settle –