We wish to advise that work continues to progress well.
Please see the construction update below:
Works planned on site for the next 6 months
Site Possession – 01 September 2022 | Anticipated Project Completion – Early 2025
Estimated timeframe: 30 month single stage development
Site Establishment
- Site Accommodation and Setup
- Hoardings and Fences
- Disconnection of Services
- Temporary construction power and water
- Tree protection
Services Infrastructure
- Stormwater upgrade on Horsley Avenue
- Power upgrade to site
Demolition
- Removal of all items that need to salvaged from the club to be reimagined in the new development
- Demolition of Club Willoughby buildings
- Site clearing
Shoring
- Preparation of piling platform
- Piling around the perimeter of the site
Excavation
- Bulk Excavation
Click here to view Hyegrove Willoughby construction timeline and 360-degree views.