Milestones

  • Partial completion of the podium common areas.
  • All the projects landscaping has now been completed including all street trees.
  • Construction of the new cul-de-sac and road leading into the development is almost complete.
  • Target for occupational certification will be obtained by December 2021.
  • Strata registration was obtained.
Works planned to finalise Elena:
  • Fit out of the amenities.
  • Completion of the footpath, kerb and gutters.
  • Final detail work to apartments.