Estimated Construction Completion: Q4 2025
Estimated Settlement: Q4 2025
Click here to view a timeline of the build go to our 360 photo captured in January 2025
We wish to advise that building work continues to progress well. Please see the construction update below:
Milestones:
Works completed from previous quarter
(October – December 2024):
- Completion of blockwork in the basement.
- Overhead services installation in basements 4, 3, 2 & 1 complete.
- Formwork, Reo, PT and Pour: (L3-L9)
- Delivery of Lifts to Site.
- Man, and Material Hoist installed.
- Stripping of levels Ground Floor, Lower Ground Floor: (L1-L5)
- Prepare wet areas for the commencement of waterproofing Ground and Upper Ground Floor – Level 1.
- Commencement of internal framing (L1-L2)
- Commencement of external framing and Installation of window and door sub jambs, subheads and sub sills. (L1)

Works planned on site for the next quarter
(January – March) of 2025:
- Formwork, Reo, PT and Pour: (L10-L16)
- Stripping of levels Ground Floor, Lower Ground Floor: (L6-L12)
- Installation of split deck
- Commencement of external framing and Installation of window and door sub jambs, subheads and sub sills. (L2-L10)
- Commencement of internal framing and hebel walls (L3-L10)
- Completion of internal framing and hebel walls (L1-L6)
- Prepare wet areas for the commencement of waterproofing (L2-L7)
- Commencement of Internal Fitout (L1-L5)
- Commencement of Carpark preparation and Fitout
- Commencement carpark painting
- Commencement of Mains Water Upgrade
Programme
The key programme items are as follows:
- Site set up works Completed
- Bulk excavation Completed
- Basement works Completed
- Structure works In-Progress
- Services rough in In-Progress
- Window glazing In-Progress
- Facade cladding In-Progress
- Internal fit out works In-Progress
- Finishing works Not started
- Landscaping Not started
- Title registration Not started
- Ready to settle –
Next Update: April 2025