Construction Update – Audrey

February 2025

Estimated Construction Completion: Q4 2025
Estimated Settlement: Q4 2025

Click here to view a timeline of the build go to our 360 photo captured in January 2025

We wish to advise that building work continues to progress well. Please see the construction update below:

Milestones:

Works completed from previous quarter
(October – December 2024):

  • Completion of blockwork in the basement.
  • Overhead services installation in basements 4, 3, 2 & 1 complete.
  • Formwork, Reo, PT and Pour: (L3-L9)
  • Delivery of Lifts to Site.
  • Man, and Material Hoist installed.
  • Stripping of levels Ground Floor, Lower Ground Floor: (L1-L5)
  • Prepare wet areas for the commencement of waterproofing Ground and Upper Ground Floor – Level 1.
  • Commencement of internal framing (L1-L2)
  • Commencement of external framing and Installation of window and door sub jambs, subheads and sub sills. (L1)

Works planned on site for the next quarter
(January – March) of 2025:

  • Formwork, Reo, PT and Pour: (L10-L16)
  • Stripping of levels Ground Floor, Lower Ground Floor: (L6-L12)
  • Installation of split deck
  • Commencement of external framing and Installation of window and door sub jambs, subheads and sub sills. (L2-L10)
  • Commencement of internal framing and hebel walls (L3-L10)
  • Completion of internal framing and hebel walls (L1-L6)
  • Prepare wet areas for the commencement of waterproofing (L2-L7)
  • Commencement of Internal Fitout (L1-L5)
  • Commencement of Carpark preparation and Fitout
  • Commencement carpark painting
  • Commencement of Mains Water Upgrade

Programme

The key programme items are as follows:

  1. Site set up works Completed
  2. Bulk excavation Completed
  3. Basement works Completed
  4. Structure works In-Progress
  5. Services rough in In-Progress
  6. Window glazing In-Progress
  7. Facade cladding In-Progress
  8. Internal fit out works In-Progress
  9. Finishing works Not started
  10. Landscaping Not started
  11. Title registration Not started
  12. Ready to settle –

Next Update: April 2025