Estimated Construction Completion: Q4 2025
Estimated Settlement: Q4 2025
Click here to view a timeline of the build go to our 360 photo captured in July 2024
We wish to advise that building work continues to progress well. Please see the construction update below:
Milestones:
Works completed from Start to (July-September 2024) Quarter:
- Bulk & Detail Excavation Complete
- Shoring and Anchors Complete
- Tower Crane Erected
- In-Ground Services Complete
- All pad footings and lifts poured
- Basement Pump-Out Tank Poured & Pump Installed
- Slab on Ground Poured
- All Ramps Between and including Basement 4 – Ground Floor Poured
- 100% of Basement Level 4 – Basement Level 1, Concrete Slabs Poured
- 100% of Ground Floor to Level 2 Concrete Slabs Poured
- Formwork, Reinforcement and Post Tension Working on Level 3
- Scaffolding topped up to Level 3.
- Sewer works complete from site boundary to main sewer.
- Formwork stripping continues in basements levels 3, 2 & 1.
- Overhead services installation commenced in basements 4, 3 & 2
- Substation chamber poured
- Fire Tank Poured
Works planned on site for the next quarter of 2024:
Works planned on site for the next quarter (October – December) of 2024:
- Commencement of blockwork in the basement
- Overhead services installation in basements 4, 3, 2 & 1 complete
- Formwork, Reo, PT and Pour: (L3-L8)
- Delivery of Lifts to Site.
- Man, and Material Hoist installed.
- Stripping of levels Ground Floor, Lower Ground Floor: (L1-L4)
- Commencement of external framing and Installation of window and door sub jambs, subheads and sub sills. (Ground, Upper Ground Floor and L1)
- Prepare wet areas for the commencement of waterproofing
Ground and Upper Ground Floor - Commencement of internal framing Ground, Upper Ground Floor and Level 1
- Installation of Lift 03
Works planned on site for quarter (January – March) of 2025:
- Completion of blockwork in basement
- Completion of services in basement
- Completion of Rendering and Painting in Basement
- Carpark fit out Commencement
- Formwork, Reo, PT and Pour: (L9 – L17)
- External framing and Installation of window and door sub jambs, subheads and sub sills: (L2 – L13)
- External Cladding / Façade Finishes / Louvres & Balustrades: (L2 – L10)
- Internal Services and fit out Commencement and On-going: (L2-L13)
- Commencement of Lift 1 & 2 installation
Programme
The key programme items are as follows:
- Site set up works Completed
- Bulk excavation Completed
- Basement works Completed
- Structure works In-Progress
- Services rough in In-Progress
- Window glazing In-Progress
- Facade cladding Not started
- Internal fit out works Not started
- Finishing works Not started
- Landscaping Not started
- Title registration Not started
- Ready to settle –
Next Update: January 2025