Construction Update – Audrey

April 2024

Estimated Construction Completion: Q4 2024
Estimated Settlement: Q2 2025

Click here to view a timeline of the build go to our 360 photo captured in April 2024

Milestones:

  • Bulk & Detail Excavation Complete
  • Shoring and Anchors Complete
  • Tower Crane Erected
  • In-Ground Services Complete
  • All pad footings and lifts poured
  • Basement Pump-Out Tank Poured & Pump Installed
  • Slab on Ground Poured
  • Ramp Between Basement 4 and 3 Poured 100% of Basement Level 3 Poured
  • Ramp Between Basement 3 and 2 Poured 100% of Basement Level 2 Poured
  • Ramp Between Basement 2 and 1 Poured 100% of Basement Level 1 Poured
  • Formwork, Reinforcement and Post Tension Installed on Pour 1 on Ground Floor
  • Formwork deck complete on Pours 2 & 3 on Ground Floor
  • Sewer works complete from site boundary to main sewer.
  • Formwork stripping has commenced in basement 3 & 2
  • Overhead services installation commenced in basements 3 & 2

Works planned on site for the next quarter of 2024:

  • 100% of Ground Floor Concrete Slabs Poured
  • Perimeter Scaffold Installation upto and including level 5
  • Undergrounding of Overhead Powerlines across Canberra Avenue frontage
  • OSD Tank, Pool and Fire Tanks to be poured
  • Commencement of blockwork in the basement
  • Formwork, Reo, PT and Pour to Levels Upper Ground, 1, 2, 3, 4 & 5
  • Overhead services installation in basements 4, 3, 2 & 1 complete
  • Man and Material Hoist installed.
  • Commencement of external framing and Installation of window and door sub jambs, sub heads and subsills.

Programme

The key programme items are as follows:

  1. Site set up works Completed
  2. Bulk excavation Completed
  3. Basement works Completed
  4. Structure works In-Progress
  5. Services rough in In-Progress
  6. Window glazing Not started
  7. Facade cladding Not started
  8. Internal fit out works Not started
  9. Finishing works Not started
  10. Landscaping Not started
  11. Title registration Not started
  12. Ready to settle –

Next Update: July 2024