Estimated Construction Completion: Q4 2024
Estimated Settlement: Q2 2025
Milestones:
- Bulk & Detail Excavation Complete
- Shoring and Anchors Complete
- Tower Crane Erected
- In-Ground Services Complete
- All pad footings and lifts poured
- Basement Pump-Out Tank Poured & Pump Installed
- Slab on Ground Poured
- Ramp Between Basement 4 and Basement 3 Poured
- 70% of the first Suspended Slab on Basement Level 3 Poured
Works planned on site for the first quarter of 2024:
- 100% of Basement Concrete Slabs Poured
- Completion of In-Ground Waterproofing
- Commencement of Ground Floor Transfer Slab
- Commencement of Perimeter Scaffold Installation
- Undergrounding of Overhead Powerlines across Canberra Avenue frontage
- Connection of Minor Sewer Works
Programme
The key programme items are as follows:
- Site set up works Completed
- Bulk excavation Completed
- Basement works Completed
- Structure works In Progress
- Services rough in Not started
- Window glazing Not started
- Facade cladding Not started
- Internal fit out works Not started
- Finishing works Not started
- Landscaping Not started
- Title registration Not started
- Ready to settle –