Construction Update – Audrey

January 2024

Estimated Construction Completion: Q4 2024
Estimated Settlement: Q2 2025

Milestones:

  • Bulk & Detail Excavation Complete
  • Shoring and Anchors Complete
  • Tower Crane Erected
  • In-Ground Services Complete
  • All pad footings and lifts poured
  • Basement Pump-Out Tank Poured & Pump Installed
  • Slab on Ground Poured
  • Ramp Between Basement 4 and Basement 3 Poured
  • 70% of the first Suspended Slab on Basement Level 3 Poured

Works planned on site for the first quarter of 2024:

  • 100% of Basement Concrete Slabs Poured
  • Completion of In-Ground Waterproofing
  • Commencement of Ground Floor Transfer Slab
  • Commencement of Perimeter Scaffold Installation
  • Undergrounding of Overhead Powerlines across Canberra Avenue frontage
  • Connection of Minor Sewer Works

Programme

The key programme items are as follows:

  1. Site set up works Completed
  2. Bulk excavation Completed
  3. Basement works Completed
  4. Structure works In Progress
  5. Services rough in Not started
  6. Window glazing Not started
  7. Facade cladding Not started
  8. Internal fit out works Not started
  9. Finishing works Not started
  10. Landscaping Not started
  11. Title registration Not started
  12. Ready to settle –