Estimated Construction Completion: Q4 2024
Click here to view Audrey St.Leonards construction timeline and 360-degree views.
We wish to advise that building work continues to progress well.
Please see the construction update for the past quarter below:
Milestones:
- Site Set-Up Work Complete
- Bulk Excavation Commenced
- Tower Crane Design Finalised
Works planned on site for the next quarter of 2023:
- Continuation of Bulk Excavation to Basement Level 4
- Preparation for Slab on Ground
- Installation of Tower Crane
- Commence Undergrounding Cabling of Power Lines
Programme
The key programme items are as follows:
- Site set up works – Completed
- Bulk excavation – Not started
- Basement works – Not started
- Structure works – Not started
- Services rough in – Not started
- Window glazing – Not started
- Facade cladding – Not started
- Internal fit out works – Not started
- Finishing works – Not started
- Landscaping – Not started
- Title registration – Not started
- Ready to settle –