Construction Update – Audrey

April 2023

Estimated Construction Completion: Q4 2024

We wish to advise that building work continues to progress well.
Please see the construction update for the past quarter below:

Milestones:

  • Site Set-Up Work Complete
  • Bulk Excavation Commenced
  • Tower Crane Design Finalised

Works planned on site for the next quarter of 2023:

  • Continuation of Bulk Excavation to Basement Level 4
  • Preparation for Slab on Ground
  • Installation of Tower Crane
  • Commence Undergrounding Cabling of Power Lines

Programme

The key programme items are as follows:

  1. Site set up worksCompleted
  2. Bulk excavation – Not started
  3. Basement works – Not started
  4. Structure works – Not started
  5. Services rough in – Not started
  6. Window glazing – Not started
  7. Facade cladding – Not started
  8. Internal fit out works – Not started
  9. Finishing works – Not started
  10. Landscaping – Not started
  11. Title registration – Not started
  12. Ready to settle