Estimated Construction Completion: 4th quarter 2024
Click here to view Audrey St.Leonards construction timeline and 360-degree views.
We wish to advise that building work continues to progress well.
Please see the construction update for the past quarter below:
Milestones:
- Established on Site
- Demolition Commenced
Works planned on site for the next quarter of 2023:
- Complete Demolition of 4 Houses
- Commence Bulk Excavation
- Commence critical infrastructure works
Programme
The key programme items are as follows:
- Site set up works – In progress
- Bulk excavation – Not started
- Basement works – Not started
- Structure works – Not started
- Services rough in – Not started
- Window glazing – Not started
- Facade cladding – Not started
- Internal fit out works – Not started
- Finishing works – Not started
- Landscaping – Not started
- Title registration – Not started
- Ready to settle –