Construction Update – Audrey

October 2023

We wish to advise that building work continues to progress well.
Please see the construction update for the past quarter below:

Milestones:

  • Installation of Tower Crane
  • Bulk Excavation complete to Basement 3
  • Installation of Basement Scaffolding Stairs and Site Amenities

Works planned on site for the next quarter of 2023:

  • Completion of Bulk & Detail Excavation
  • Installation of in-ground stormwater system
  • Commencement of Basement Structure
  • Undergrounding of Overhead Powerlines across Canberra Avenue frontage
  • Connection of Minor Sewer Works

Programme

The key programme items are as follows:

  1. Site set up worksCompleted
  2. Bulk excavation – In Progress
  3. Basement works – Not started
  4. Structure works – Not started
  5. Services rough in – Not started
  6. Window glazing – Not started
  7. Facade cladding – Not started
  8. Internal fit out works – Not started
  9. Finishing works – Not started
  10. Landscaping – Not started
  11. Title registration – Not started
  12. Ready to settle