Estimated Construction Completion: Q4 2024
Estimated Settlement: Q1 2025
Click here to view Audrey St.Leonards construction timeline and 360-degree views.
We wish to advise that building work continues to progress well.
Please see the construction update for the past quarter below:
Milestones:
- Installation of Tower Crane
- Bulk Excavation complete to Basement 3
- Installation of Basement Scaffolding Stairs and Site Amenities
Works planned on site for the next quarter of 2023:
- Completion of Bulk & Detail Excavation
- Installation of in-ground stormwater system
- Commencement of Basement Structure
- Undergrounding of Overhead Powerlines across Canberra Avenue frontage
- Connection of Minor Sewer Works
Programme
The key programme items are as follows:
- Site set up works – Completed
- Bulk excavation – In Progress
- Basement works – Not started
- Structure works – Not started
- Services rough in – Not started
- Window glazing – Not started
- Facade cladding – Not started
- Internal fit out works – Not started
- Finishing works – Not started
- Landscaping – Not started
- Title registration – Not started
- Ready to settle –